Uncertainty
Sep. 12th, 2006 05:27 pmJust went to a neat seminar about project management and estimating how much time a project will take.
The interesting thing about it is that the hardest part of managing uncertainty is getting people to admit, even to themselves, that things are as likely to come in above the mean as they are under the mean. Once you've overcome that psychological barrier, thinking rationally about it is pretty easy, folks are just really loathe to acknowledge the possibility -- the likelihood, even -- that things will go wrong.
The interesting thing about it is that the hardest part of managing uncertainty is getting people to admit, even to themselves, that things are as likely to come in above the mean as they are under the mean. Once you've overcome that psychological barrier, thinking rationally about it is pretty easy, folks are just really loathe to acknowledge the possibility -- the likelihood, even -- that things will go wrong.
no subject
Date: 2006-09-13 05:05 pm (UTC)See some of the other comments, also. Part of the idea is that if you're doing it this way, people shouldn't need to sandbag, because the safety margins have been taken care of explicitly.
I guess the question is, why are the managers trying to squeeze the extra out? Their part of the project came in early and under budget -- isn't that good? Do they want to increase the odds of having late penalties associated with their work?
no subject
Date: 2006-09-13 05:26 pm (UTC)Sadly, I have often found it is to my benefit to goof around to use up my cushion rather than turn in work early because I might need that cushion next time and my employers don't understand the uncertainties associated with scheduling. My favorite example was when the MBA running one project asked us to give her a precise estimate on when we would make what was basically a scientific breakthrough. She needed it for her Gantt chart. We tried to explain to her that we didn't know when we'd figure it out; it would depend on how the experiments went. She wouldn't budge. We made up a number; it was easier than arguing.
There are also often business pressures that are swept out of sight and treated as assertions e.g. "It must be done by Date X, and it must include all of these features or we won't be successful". In an open, honest work environment, there could be a rational discussion where the realistic estimates of what it takes to accommodate those features would be balanced with the business cases for each feature. Unfortunately, most work environments are not like that. Instead, the communication is happening through a game of Telephone such that that discussion can't take place.
no subject
Date: 2006-09-13 05:31 pm (UTC)no subject
Date: 2006-09-13 05:46 pm (UTC)Our prof said last night that a recent survey of IT projects showed that 22% were completed within the original estimate, 52% were late by an average of 100% (double the original estimate), and 26% never finished. And developers wonder why their estimates have no credibility. Admittedly, many of those estimates were poorly constructed because of management pressures, etc., but there's definitely a competitive advantage to being able to deliver on time repeatedly.
Then again, most people don't want to hear how long a software project will actually take. "It's just software! Why does it take that long?!" So even if you give them realistic estimates, they don't believe them.
I am full of cynicism and bitterness. Can you tell?
no subject
Date: 2006-09-13 05:28 pm (UTC)no subject
Date: 2006-09-24 09:48 pm (UTC)Now that they’ve reorged our company and gotten rid of all the project managers, it falls on me (as the QA guy) to give daily reports to the CFO about why the IT projects aren’t on schedule.
So I feel like maybe I should find out what the Hell you guys are talking about in this thread.
no subject
Date: 2006-09-25 02:15 am (UTC)If you've got something that follows a normal distribution (aka Gaussian distribution or bell curve), the variability of the distribution (the standard deviation) is customarily represented by the letter sigma. It's a measure of how wide the curve is.
The useful thing is that about 2/3 of the area under the curve is between (mean+sigma) and (mean-sigma). If you go out to 2 sigma on either side of the peak/center, you've got 95% of the area, and 3 sigma gets you to about 99%.
So if I do an estimate the way this guy described and it tells me that, on average, my project will take 20 weeks, with a standard deviation of 3 weeks, I know that I can come in under deadline 97.5% of the time if I commit to doing it in 26 weeks (+2 sigma). [That's assuming that the estimate is accurate, of course.]